Construction Progress Report 7-27-12
Last Updated on 17 September 2012
Weekly Progress Update, Week Ending September 14, 2012
Structural Steel parapet at East building is ongoing
- 1st Floor stud framing at North and Central building is complete
- Completed decking at East building
- HVAC ductwork started at 1st Floor Center building
- MEP rough in continuing at all buildings
- Windscreen was installed at Tennis Courts
- Continued punchlist work for Tennis Court Interior and Site paving
- Completed slab pour at East building elevator and stairs
- Completed concrete pour at South building walkway and 2nd Floor East building
Next Week's Activities
- Start densglass at 1st Floor of North building
- Hoist roof curbs to all buildings
- Complete Structural Steel East building parapet
- Complete 1st Floor installation of hollow metal frames at South, Center, and North buildings
- Continue roof drain tie in at all buildings
- MEP ongoing inside all buildings
- Start forming up curbs at 2nd Floor East building and elevator location
Upcoming Meetings
- Owner, Architect, Riha and Turner meetings will be held on September 18 at 10:30am