Weekly Progress Update, Week Ending February 1, 2013
Ø Completed paint on exterior of North Building.
Ø Continued drywall installation at East Building.
Ø Continued exterior lathing of East Building stairwell.
Ø Interior prime and paint was continued at South Building.
Ø Started paint on exterior of Center Building
Ø Base and mesh application of plaster system was continued at Central Building.
Ø Scratch and brown application of plaster system was continued at South Building.
Ø Scratch and brown application started at East Building at East face.
Ø Plumbing continued at East Building.
Ø Began suspended ceiling installation at North Building.
Ø Started removing scaffolding at Center Building
Next Week’s Activities
Ø Continue suspended ceiling installation at North Building and start on Center Building.
Ø Continue plumbing installation at East Building
Ø Continue drywall installation at East Building.
Ø Complete painting interior of South Building.
Ø Start mesh and base application of plaster system on South Building.
Ø Complete exterior paint of Center Building.
Ø Start hanging exterior doors on North Building
Ø Continue plaster installation at East Building.
Upcoming Meetings
Ø Owner, Architect, Riha, and Turner meetings will be held on February 5, 2013 at 10:00am